Irish Water seeks CPOs to progress upgrade to Athlone's main drainage sewer network

Aug 6, 2021 07:45 By Shannonside News
Irish Water seeks CPOs to progress upgrade to Athlone's main drainage sewer network
Share this article

No homes or households are being acquired through the CPO

Irish Water has applied for permission for compulsory purchase orders to progress a major sewerage scheme in Athlone.

It's after discussions with landowners for the purchase of the lands collapsed.

The state body is seeking permission to acquire wayleaves and lands for the Athlone Main Drainage Sewer Network upgrade.

Advertisement

The project involves the construction of new pumping stations in Golden Island and Coosan West, and the construction of almost 3km of sewer network

Consultations have been on-going with landowners, however, Irish Water was unable to acquire all of the required wayleaves and lands on a voluntary basis and has submitted an application for a Compulsory Purchase Order (CPO) to An Bord Pleanála.

However no homes or households are being acquired through the CPO.

Advertisement

It is expected that the construction contract will be signed in the second half of 2022 and information events for businesses, residents and elected representatives will be held prior to the commencement of works.

Share this article
Advertisement
Advertisement

Shannonside Newsletter

Sign up now to keep up to date with the latest news.

Processing your request...

You are subscribed now! please check your email to confirm your subscription.

Copyright © 2024 Shannonside FM. Developed by Square1 and Powered by PublisherPlus